We Beat Any Written Quote | Call Now 1300 553 173

Melbourne VIC Wide Home & Commercial Drainage Plumber, Pipe Relining & Blocked Drains Specialists

Project

Westwood Place R8 Wetlands Desludging

Location

North-west Melbourne, VIC

Scope

Approx. 150,000 kg of wet sediment and debris removed

Duration

10 working days

Services

Desludging, Waste Removal

Client Type

Civil Contractors & Infrastructure

Overview

LCL Plumbing & Drainage was engaged to complete maintenance desludging of the Westwood Place R8 wetland ahead of its planned handover to Melbourne Water. The pond held significant sediment, organic material and construction debris, with deposits reaching around 1100 mm deep. Persistent rain kept pushing water back into the basin, so the works needed a practical wet-weather methodology to control live water, protect the established wetland surrounds, and manage saturated material through drying, transport and off-site disposal. Roughly 150 tonnes was removed in ten working days.

The Challenge

  • Heavy sediment and debris build-up of up to approximately 1.1 metres.
  • Persistent rain repeatedly introduced water back into the pond.
  • Soft ground at the temporary drying and tipping area constrained material handling.
  • Live water and established wetland surrounds required careful access and control.

Our Solution

  • Pipe plugs isolated inflows where applicable to support controlled dewatering.
  • Vacuum trucks and a six-inch water pump removed water and saturated sediment in stages.
  • A skid steer managed material within the basin and the nearby drying area.
  • Material was dried, transported off-site, and the pond was final-cleaned and inspected.

Delivery Sequence

  1. Control inflows and manage water levels.
  2. Pump standing water to expose the sediment profile.
  3. Vacuum-extract saturated material in stages.
  4. Use the skid steer to consolidate material and maintain access.
  5. Dry material, load tandem trucks and transport off-site.
  6. Remove remaining debris, clean down and verify completion.

Quality and Site Controls

  • Staged dewatering and extraction to maintain control of live water.
  • Pipe-plug isolation where applicable.
  • Designated drying area for saturated material.
  • PPE and separation of workers from operating plant.
  • Ongoing adjustment to rainfall, soft ground and changing water levels.

Result

The nominated debris and sediment were removed, leaving the wetland pond cleaned and ready to progress through the planned Melbourne Water handover process. Completing the works in ten working days while responding to ongoing rain, live water and soft-ground constraints showed what a focused crew and fit-for-purpose plant can deliver on large-scale wetland maintenance.

Contact Us

Request a Free
Quote Today

Tell us what you need, and our team will get back to you ASAP.