Overview
LCL Plumbing & Drainage delivered the complete below-ground drainage package for a new childcare centre and adjoining retail buildings at Nile Drive, Truganina. The works covered sewer, stormwater and trade waste infrastructure, supported by civil trenching, soil removal and coordinated service installation. With multiple buildings and underground services across the one site, accurate set-out, levels and grades were critical. Leica GPS equipment positioned drainage routes, pits and associated infrastructure before installation, then recorded the completed assets for reliable as-built documentation.
The Challenge
- Coordinate drainage across multiple childcare and retail building zones.
- Maintain precise positions, levels and grades around other underground services.
- Install large-diameter stormwater and specialised trade waste infrastructure efficiently.
Out Solution
- Leica GPS set-out accurately positioned drainage routes, pits and service points.
- StormPRO up to 600 mm, concrete pits, charged lines, grease traps and cooling pits were installed in coordinated stages.
- GPS data was captured during construction to provide accurate completed as-built information.
Scope of Works
- Install all below-ground sewer and stormwater drainage.
- Install charged stormwater lines and trade waste drainage.
- Supply and install grease traps, cooling pits and concrete stormwater pits.
- Install StormPRO stormwater pipework up to 600 mm diameter.
- Excavate and construct service trenches, including removal of excess soil.
- Complete GPS set-out, surveying and final as-built information.
Delivery Sequence
- Set out and verify. Leica GPS established the precise routes, pit positions and service points before installation.
- Excavate and prepare. Service trenches and pit locations were excavated while coordinating access and other site activities.
- Install and connect. Sewer, stormwater, charged lines and trade waste infrastructure were installed to the required levels and grades.
- Backfill and reinstate. Approved material was placed and compacted, with excess excavated soil removed from site.
- Record and document. GPS data was captured to provide accurate as-built records for the customer and future reference.
Quality and Documentation
GPS data was recorded throughout construction to document the completed underground services. The final as-built information provides a reliable record of drainage locations for future construction, maintenance and service coordination.
Result
A coordinated, accurately set-out below-ground drainage package was delivered across the development, providing complete sewer, stormwater and trade waste infrastructure with reliable GPS as-built documentation. Combining experienced installation practices with Leica GPS set-out and recording meant the underground services went in accurately and the customer received dependable as-built information at completion.